Anyone willing to share a stage-gate playbook that ties AFE, long-lead, and pre-spud HAZID to clear RACIs and MOC triggers? We’re running two rigs 24/7 with a 6-week lookahead, and I want a template that drives safety-critical checks before spud and at TD-to-handover, not just paperwork?
And > a template that drives safety-critical checks before spud and at TD-to-handover, Agree — running two rigs 24/7 we set a T-42 Long-Lead Freeze tied to AFE release with auto-MOC for any post-freeze change to BOP stack, casing grade, or MW window; T-14 pre-spud HAZID with Supt=A, Company Man=R, HSE=C; at TD we use a D-010 barrier check and an evidence pack gate before handover. Want the one-pager RACI/MOC template with the 6-week lookahead baked in?
Paperwork for the sake of it drives me nuts; with a 6‑week lookahead, we run a T‑10 “before spud” Red‑Gate that hard-stops unless three things are attached: signed barrier schematic (WE + HSE), BOP test window confirmed, and LL QA/COC packs with named RACI owners. Auto‑MOC triggers on any casing/tubular spec change, MW delta >0.3 ppg, or safety‑critical vendor swap; TD‑to‑handover requires dual‑barrier verification per NORSOK D‑010 (see https://www.standard.no/en/sectors/energy/norsok-standards/d-010-well-integrity-in-drilling-and-well-operations/). Want my one‑pager checklist template?